- Milestone
- A defined point in the project schedule β typically the completion of a phase or delivery of a major output β that triggers a review, payment, or next-phase authorization.
- Deliverable
- A specific, tangible output that must be produced and accepted by a defined date, such as a completed design, compiled software build, or signed-off report.
- Critical Path
- The sequence of dependent tasks that determines the minimum total duration of the project β any delay on the critical path delays the final completion date.
- Float (Slack)
- The amount of time a task can be delayed without pushing back the project's overall completion date or the next dependent milestone.
- Baseline Schedule
- The original, agreed-upon project timeline at contract execution, preserved as a reference point against which all subsequent changes and delays are measured.
- Change Order
- A written amendment to the project scope, schedule, or budget agreed by both parties, which may extend milestone dates or add new deliverables.
- Liquidated Damages
- A pre-agreed sum the contractor or service provider pays for each day the project runs past a contractual completion date, set in advance as an estimate of the owner's loss.
- Force Majeure
- A clause excusing a party from performance obligations when an unforeseeable event beyond their control β such as a natural disaster or government order β prevents timely completion.
- Substantial Completion
- The stage at which a project is sufficiently complete for its intended use, even if minor punch-list items remain β often the trigger for final payment release.
- Notice to Proceed
- A formal written instruction from the project owner or client authorizing the contractor or service provider to begin work, typically starting the clock on the first milestone.
- Acceptance Criteria
- The specific, measurable conditions a deliverable must satisfy before the client is obligated to formally approve it and release the associated payment.