- Scope Statement
- A written description of what the project will and will not deliver, used as the baseline against which all change requests are evaluated.
- Work Breakdown Structure (WBS)
- A hierarchical decomposition of the total project scope into smaller, manageable deliverables and work packages.
- Milestone
- A significant scheduled event or completion point in a project that marks the end of a phase or delivery of a key output.
- Critical Path
- The longest sequence of dependent tasks in a project schedule β any delay on the critical path delays the project end date.
- Risk Register
- A log of identified project risks, each rated by probability and impact, with assigned owners and mitigation or contingency actions.
- RACI Matrix
- A responsibility assignment chart that maps each task or deliverable to team members as Responsible, Accountable, Consulted, or Informed.
- Change Control
- A formal process for evaluating, approving, and documenting any requested modification to project scope, schedule, or budget.
- Baseline
- The approved, fixed reference point for project scope, schedule, and cost against which actual performance is measured.
- Stakeholder
- Any individual, team, or organization that has an interest in or is affected by the outcomes of the project.
- Contingency Reserve
- Budget or time set aside to cover identified risks that materialize during the project, distinct from management reserve held for unknown risks.
- Project Sponsor
- The senior person who authorizes the project, owns the business case, and resolves escalated issues beyond the project manager's authority.