- Scope of Work
- The detailed written description of all construction tasks, materials, and deliverables the contractor is obligated to complete under the contract.
- Change Order
- A written amendment to the original contract that documents a change in scope, cost, or schedule agreed to by both parties after execution.
- Retainage
- A percentage of each progress payment — typically 5–10% — withheld by the owner until substantial completion, protecting against incomplete or defective work.
- Substantial Completion
- The point at which the project is sufficiently complete for the owner to occupy or use it for its intended purpose, even if minor punch-list items remain.
- Lien Waiver
- A document signed by a contractor or subcontractor confirming they have been paid and waiving their right to file a mechanic's lien against the property for that payment.
- Mechanic's Lien
- A legal claim filed against a property by an unpaid contractor, subcontractor, or supplier, which can encumber the title until the debt is resolved.
- Performance Bond
- A surety bond guaranteeing that the contractor will complete the project according to the contract terms, protecting the owner if the contractor defaults.
- Liquidated Damages
- A pre-agreed daily or weekly dollar amount the contractor pays the owner for each day the project exceeds the contracted completion date, set in the contract rather than litigated after the fact.
- Force Majeure
- A clause excusing a party from performance obligations due to extraordinary events outside their control — such as natural disasters, strikes, or material shortages.
- Punch List
- A list of minor outstanding tasks or defects identified at or near substantial completion that the contractor must remedy before final payment is released.
- Indemnification
- A contractual obligation by one party to compensate the other for specified losses, damages, or legal costs arising from the indemnifying party's actions or negligence.
- Contract Price
- The total amount the owner agrees to pay the contractor for completing the defined scope of work, stated as a lump sum, guaranteed maximum price, or cost-plus formula.