Subcontract Agreement Template

Free Word download β€’ Edit online β€’ Save & share with Drive β€’ Export to PDF

4 pagesβ€’25–30 min to fillβ€’Difficulty: Complexβ€’Signature requiredβ€’Legal review recommended
Learn more ↓
FreeSubcontract Agreement Template

At a glance

What it is
A Subcontract Agreement is a legally binding contract between a prime contractor and a subcontractor that delegates a defined portion of work from a larger project. This free Word download lets you specify the scope, schedule, payment terms, liability allocation, and IP ownership before a single hour of subcontracted work begins β€” then export as PDF for signature.
When you need it
Use it whenever you engage a third-party trade, specialist, or service provider to perform work that you have already contracted to deliver for a client. It is essential before any subcontractor mobilizes on-site or begins billable work.
What's inside
Scope of work and deliverables, project schedule and milestones, payment terms and retention, insurance and bonding requirements, indemnification and liability caps, IP assignment and confidentiality, change-order procedures, termination for cause or convenience, and dispute resolution.

What is a Subcontract Agreement?

A Subcontract Agreement is a legally binding contract between a prime contractor and a subcontractor that formally delegates a defined portion of a larger project. Where the prime contractor holds the main obligation to deliver a project for a client, the subcontract carves out a specific scope β€” a trade package, a development sprint, a specialist analysis β€” and creates enforceable obligations for that portion: price, schedule, insurance, liability, IP ownership, and compliance. Unlike a direct service agreement, a subcontract sits within a contract chain, meaning the subcontractor's obligations are shaped both by the subcontract itself and by the upstream prime contract through flow-down clauses. A properly drafted subcontract protects the prime contractor's position with the client while giving the subcontractor clarity on exactly what they are being paid to do and when.

Why You Need This Document

Operating without a written subcontract exposes a prime contractor on every front simultaneously. Without a detailed scope exhibit, trade boundaries blur and subcontractors claim extras for work that was always intended to be included β€” change-order disputes on construction projects routinely exceed 10–15% of the original subcontract value. Without an IP assignment clause, a subcontractor who develops custom software, designs, or specifications may retain copyright, leaving the prime without the right to use the deliverable it paid for. Without a termination-for-convenience clause, removing an underperforming subcontractor mid-project can trigger a claim for lost profits on the entire remaining contract value. Lien rights, retainage mechanics, insurance verification, and flow-down compliance all depend on written terms that oral arrangements simply cannot provide. This template gives you a complete, jurisdiction-aware starting point that closes each of those gaps β€” reducing the cost of a first project subcontract from a lawyer's drafting fee to the time it takes to complete an exhibit.

Which variant fits your situation?

If your situation is…Use this template
Engaging a trade contractor for a residential or commercial buildConstruction Subcontract Agreement
Subcontracting software development or IT servicesIT Services Subcontract Agreement
Delegating work to a sole-trader individual rather than a companyIndependent Contractor Agreement
Engaging a consultant for a time-and-materials advisory engagementConsulting Agreement
Subcontracting on a US federal government prime contractFederal Subcontract Agreement (FAR-compliant)
Short-term or single-task subcontract with minimal deliverablesSimple Service Agreement
Creative or marketing work delegated by an agency to a freelancerFreelance Services Agreement

Common mistakes to avoid

❌ Using the prime contract's scope without a dedicated subcontract scope exhibit

Why it matters: Referencing the prime contract scope without carving out the subcontractor's specific portion creates overlapping responsibilities with other trades and makes scope disputes almost inevitable.

Fix: Draft a standalone Exhibit A that describes only the subcontractor's work, references specific drawing and specification numbers, and lists explicit exclusions.

❌ Including a pay-if-paid clause without checking local law

Why it matters: Pay-if-paid clauses are void or unenforceable in California, New York, and several other US states and Canadian provinces β€” using one gives you a false sense of protection against client non-payment.

Fix: Replace pay-if-paid with a pay-when-paid clause that sets a reasonable outside payment date (e.g., 45 days after application), which is enforceable in most jurisdictions.

❌ Accepting a certificate of insurance without verifying additional insured status

Why it matters: A certificate of insurance is not a policy β€” it does not create coverage. If the endorsement naming you as additional insured is missing from the underlying policy, you have no protection in the event of a claim.

Fix: Request a copy of the additional insured endorsement (typically CG 20 10 and CG 20 37 for construction) from the subcontractor's broker before allowing work to begin.

❌ Omitting a written change-order requirement and approving scope verbally

Why it matters: Verbal approvals for extra work are routinely disputed when the project goes over budget. Without a signed change order, the subcontractor typically cannot recover additional compensation even if the work was clearly requested.

Fix: Train all project managers to issue a written change order β€” even a short email confirmation β€” before any out-of-scope work begins, and include this requirement explicitly in the contract.

❌ Flowing down the full prime-contract liquidated damages rate to a single subcontractor

Why it matters: If a subcontractor's delay is only one of several potential causes of project overrun, courts may void an LD provision that holds them responsible for the entire daily rate as disproportionate to actual damages.

Fix: Calibrate the subcontractor's LD rate to reflect their share of the critical path and the damages their specific delay would cause, supported by a project schedule analysis.

❌ No termination for convenience clause

Why it matters: Without a termination-for-convenience right, removing a subcontractor for any reason other than default may entitle them to claim lost profits on the full remaining contract value β€” a significant financial exposure on large projects.

Fix: Include a standard termination-for-convenience clause limiting the subcontractor's recovery to work satisfactorily completed plus demobilization costs, explicitly excluding lost profit on unperformed work.

The 10 key clauses, explained

Parties, recitals, and prime contract reference

In plain language: Identifies the prime contractor and subcontractor by full legal name and entity type, states the project, and incorporates the prime contract by reference so the subcontractor is aware of upstream obligations.

Sample language
This Subcontract Agreement ('Agreement') is entered into as of [DATE] between [PRIME CONTRACTOR LEGAL NAME], a [STATE] [ENTITY TYPE] ('Contractor'), and [SUBCONTRACTOR LEGAL NAME], a [STATE] [ENTITY TYPE] ('Subcontractor'), for work on [PROJECT NAME] ('Project'). Subcontractor acknowledges receipt of the Prime Contract between Contractor and [CLIENT NAME] dated [DATE] and agrees to be bound by its terms insofar as they relate to the Subcontract Work.

Common mistake: Failing to attach or incorporate the prime contract. Without it, flow-down clauses are unenforceable and the subcontractor can claim ignorance of compliance obligations that cost the prime contractor dearly.

Scope of work and specifications

In plain language: Defines precisely what the subcontractor will deliver β€” tasks, drawings, specifications, standards, and explicit exclusions β€” so there is no ambiguity about where the subcontractor's responsibility begins and ends.

Sample language
Subcontractor shall furnish all labor, materials, tools, equipment, and supervision necessary to complete the following work ('Subcontract Work'): [DETAILED DESCRIPTION]. The Subcontract Work is more particularly described in Exhibit A (Scope of Work) and Exhibit B (Drawings and Specifications) attached hereto. The following items are expressly excluded: [LIST EXCLUSIONS].

Common mistake: Using a vague scope like 'all electrical work' without referencing specific drawings or specifications. Gaps between trades are the most common source of claims, delays, and cost overruns on construction and IT projects alike.

Schedule, milestones, and delay

In plain language: Sets the start date, key milestone dates, and final completion date β€” along with the consequences of delay, including liquidated damages where applicable.

Sample language
Subcontractor shall commence the Subcontract Work on [START DATE] and achieve Substantial Completion no later than [COMPLETION DATE]. Milestone dates are set out in Exhibit C. If Subcontractor fails to meet the Substantial Completion date, Subcontractor shall pay Contractor liquidated damages of $[AMOUNT] per calendar day of delay, which the parties agree is a reasonable estimate of damages and not a penalty.

Common mistake: Omitting an excusable delay provision. Without it, subcontractors may be held liable for delays caused by the prime contractor's own failures, client-directed changes, or force majeure events.

Contract price, payment terms, and retention

In plain language: States the total subcontract price or rate, the progress payment schedule, the retention percentage and release conditions, and any pay-when-paid or pay-if-paid provisions.

Sample language
Contractor shall pay Subcontractor the sum of $[AMOUNT] ('Subcontract Price'), subject to additions and deductions as provided herein. Progress payments of [X]% completion value shall be made within [30] days of Contractor's receipt of a compliant application. Contractor shall retain [10]% of each progress payment until Substantial Completion, reduced to [5]% upon Contractor's receipt of payment from Client.

Common mistake: Including a pay-if-paid clause β€” which conditions payment entirely on the client paying the prime β€” in a jurisdiction where such clauses are prohibited or heavily restricted. In several US states and Canadian provinces, pay-if-paid clauses are void as against public policy.

Insurance and bonding requirements

In plain language: Specifies the types and minimum limits of insurance the subcontractor must carry, names the prime contractor as additional insured, and states whether a performance or payment bond is required.

Sample language
Prior to commencing work, Subcontractor shall obtain and maintain: (a) Commercial General Liability insurance with limits not less than $[AMOUNT] per occurrence and $[AMOUNT] in the aggregate; (b) Workers' Compensation insurance as required by law; (c) Automobile Liability of not less than $[AMOUNT] combined single limit. Contractor shall be named as an additional insured on all policies. [If required:] Subcontractor shall furnish a Performance Bond and Payment Bond each in the amount of [100]% of the Subcontract Price.

Common mistake: Accepting a subcontractor's certificate of insurance without verifying that the prime contractor is actually named as additional insured on the underlying policy β€” a certificate alone provides no coverage.

Indemnification and liability

In plain language: Allocates responsibility for third-party claims, property damage, and bodily injury arising from the subcontractor's work, and caps each party's liability for indirect or consequential damages.

Sample language
Subcontractor shall defend, indemnify, and hold harmless Contractor and its officers, directors, and employees from and against any claims, damages, losses, and expenses, including reasonable attorneys' fees, arising out of or resulting from Subcontractor's performance of the Subcontract Work, to the extent caused by the negligent act or omission of Subcontractor. Neither party shall be liable for indirect, incidental, or consequential damages.

Common mistake: Using a broad-form indemnity requiring the subcontractor to indemnify the prime even for the prime's own negligence. This is unenforceable in most US states under anti-indemnity statutes and exposes the prime to voided coverage.

Intellectual property and confidentiality

In plain language: Assigns to the prime contractor (or client) all work product created by the subcontractor under the agreement, and prohibits the subcontractor from disclosing confidential project information.

Sample language
All work product, deliverables, designs, and materials created by Subcontractor in connection with the Subcontract Work ('Work Product') are works made for hire to the fullest extent permitted by law. To the extent any Work Product is not a work made for hire, Subcontractor hereby irrevocably assigns all right, title, and interest therein to Contractor. Subcontractor shall not disclose any Confidential Information of Contractor or Client to any third party without prior written consent.

Common mistake: Omitting IP assignment entirely on technology or design subcontracts. If a software developer creates custom code without a written assignment, they may retain the copyright β€” leaving the prime with no right to use the deliverable.

Change orders and scope changes

In plain language: Requires all scope, schedule, or price changes to be authorized in writing before the subcontractor performs additional work, and sets the mechanism for pricing changes.

Sample language
No change to the Subcontract Work shall be made without a written Change Order signed by both parties. Subcontractor shall not be entitled to additional compensation or time for work performed without an executed Change Order. Change Order pricing shall be based on: (a) mutual agreement; (b) unit prices set out in Exhibit D; or (c) time-and-material rates of $[RATE] per hour plus [X]% markup on materials.

Common mistake: Performing extra work on the prime contractor's verbal instruction and invoicing for it later. Courts routinely deny payment for undocumented change-order work because the written contract requires a signed amendment.

Termination for cause and for convenience

In plain language: Gives the prime contractor the right to terminate for the subcontractor's default β€” with a cure period β€” and for convenience, with payment limited to work completed to the termination date.

Sample language
Contractor may terminate this Agreement for cause if Subcontractor fails to cure a material breach within [7] days of written notice. Upon termination for cause, Contractor may complete the work by any means and charge excess costs to Subcontractor. Contractor may terminate for convenience upon [14] days' written notice, in which event Subcontractor shall be entitled to payment for Subcontract Work satisfactorily completed to the termination date, plus reasonable demobilization costs, but no lost profit on unperformed work.

Common mistake: No termination for convenience clause at all. Without it, terminating a subcontractor mid-project β€” even for business reasons β€” may entitle them to lost profits on the remaining contract value.

Dispute resolution and governing law

In plain language: Specifies which jurisdiction's law governs the agreement, whether disputes go to arbitration or court, and any notice requirements before escalating a dispute.

Sample language
This Agreement is governed by the laws of [STATE/PROVINCE/COUNTRY]. Any dispute arising under this Agreement shall first be subject to [30] days of good-faith negotiation. If unresolved, the dispute shall be submitted to binding arbitration administered by [AAA / JAMS] in [CITY], except that either party may seek injunctive relief in a court of competent jurisdiction.

Common mistake: Choosing a governing law with no connection to the project location. Several jurisdictions β€” including California and many Canadian provinces β€” apply local lien and construction law regardless of contractual choice-of-law provisions.

How to fill it out

  1. 1

    Identify both parties with full legal entity details

    Enter the prime contractor's and subcontractor's registered legal names, entity types, addresses, and authorized representative names. Confirm these match the parties' corporate registry records.

    πŸ’‘ A mismatch between the contract name and the invoicing entity name can delay payment and complicate lien rights β€” verify before signing.

  2. 2

    Attach and reference the prime contract

    Attach the prime contract or relevant excerpts as an exhibit and include a flow-down clause. This ensures the subcontractor is bound by the same compliance, safety, and IP obligations you owe the client.

    πŸ’‘ Redact the contract price from the prime contract exhibit if confidentiality is a concern β€” the subcontractor needs the scope and obligations, not the client's budget.

  3. 3

    Write a detailed scope of work with explicit exclusions

    Draft the scope as a separate Exhibit A, referencing specific drawing numbers, specification sections, and standards. List exclusions explicitly to prevent disputes about which trade is responsible for interface work.

    πŸ’‘ Walk through the scope with the subcontractor before signing and ask them to confirm in writing that they have reviewed the referenced drawings and specifications.

  4. 4

    Set milestone dates and liquidated damages

    Enter the start date, key milestone dates, and substantial completion date in Exhibit C. If the project has client-imposed liquidated damages, flow them down proportionately to the subcontractor based on their share of the critical path.

    πŸ’‘ Do not flow down the full prime-contract LD rate to a subcontractor whose delay could only cause a fraction of the total project delay β€” courts may void disproportionate LDs as penalties.

  5. 5

    Define the payment structure and retention

    State the total subcontract price, the progress payment percentage, the application and certification cycle, the retention rate, and the conditions for retention release. Confirm the payment terms comply with applicable prompt payment statutes.

    πŸ’‘ In most US states and Canadian provinces, prompt payment legislation sets maximum payment periods and interest penalties β€” your subcontract terms cannot be less favorable than these statutory floors.

  6. 6

    Specify insurance requirements and verify coverage

    Set minimum insurance limits appropriate to the project value and risk profile. Require the subcontractor to deliver a certificate of insurance naming you as additional insured before mobilization β€” then verify the endorsement is on the actual policy.

    πŸ’‘ For subcontracts over $500K, require 30 days' written notice of cancellation directly from the insurer, not just the subcontractor.

  7. 7

    Tailor the indemnity clause to your jurisdiction

    Check your state or provincial anti-indemnity statute before using broad-form indemnity language. Use intermediate-form indemnity (subcontractor indemnifies for its own negligence only) as a safe default in most US states.

    πŸ’‘ Have a construction attorney review the indemnity and insurance provisions together β€” they interact directly and a mismatch can leave you with a contractual obligation you cannot insure against.

  8. 8

    Execute before work begins and store the signed copy

    Both authorized representatives must sign before the subcontractor mobilizes. Post-start-date signatures can create enforceability gaps on restrictive clauses. Store the fully executed copy with all exhibits in a project file.

    πŸ’‘ Use a digital signature platform to timestamp execution and maintain an auditable record β€” courts in all major common-law jurisdictions accept electronic signatures under e-signature legislation.

Frequently asked questions

What is a subcontract agreement?

A subcontract agreement is a legally binding contract between a prime contractor and a subcontractor that defines the terms under which the subcontractor will perform a specified portion of a larger project. It allocates scope, schedule, payment, insurance, liability, and IP between the two parties and flows down relevant obligations from the prime contract. Unlike a direct client contract, the subcontractor's relationship is with the prime, not the end client.

What is the difference between a subcontract agreement and an independent contractor agreement?

An independent contractor agreement engages an individual or company directly for services β€” there is no upstream prime contract involved. A subcontract agreement sits within a contract chain: the prime has already committed to a client and is delegating a portion of that commitment downstream. Subcontracts typically include flow-down clauses, lien rights, bonding requirements, and retainage provisions that are absent from standard independent contractor agreements.

What should a subcontract agreement include?

At minimum: full legal names of both parties, reference to the prime contract, a detailed scope of work with explicit exclusions, project schedule and milestone dates, contract price and payment terms with retainage, insurance and bonding requirements, indemnification and liability caps, IP assignment and confidentiality, change-order procedure, termination for cause and for convenience, and governing law and dispute resolution. Missing any of these creates gaps that courts fill with jurisdiction-specific defaults, usually unfavorable to the prime.

Is a subcontract agreement legally required?

There is no universal legal requirement for a written subcontract, but public construction contracts in most US states, Canadian provinces, and the UK require written subcontracts above certain dollar thresholds. Federal government prime contracts generally mandate written subcontracts for all first-tier subcontractors. Even where not legally required, a written subcontract is essential for enforcing lien rights, retainage, non-competes, and IP assignment.

What is a flow-down clause in a subcontract?

A flow-down clause passes specific obligations from the prime contract down to the subcontractor. For example, if the prime contract requires compliance with OSHA safety standards, Davis-Bacon wage rates, or GDPR data handling, a flow-down clause makes the subcontractor equally bound. On US federal contracts, certain FAR and DFARS clauses must flow down by law. Failing to include required flow-down clauses can leave the prime in breach of its prime contract obligations.

Can a subcontractor file a lien if they are not paid?

In most US states and Canadian provinces, subcontractors have statutory lien rights β€” called mechanic's liens or construction liens β€” that allow them to encumber the project property if they are not paid for labor or materials furnished. These rights exist by statute and generally cannot be waived in advance in the contract. The prime contractor typically manages lien exposure by requiring lien waivers from each subcontractor with each progress payment.

What is retainage in a subcontract agreement?

Retainage is a percentage of each progress payment β€” typically 5–10% β€” that the prime contractor withholds until the subcontractor's work is substantially complete and accepted. It provides a financial incentive to complete punch-list items and protects the prime if defects emerge. Most US states and Canadian provinces have prompt payment statutes that regulate retainage rates, release timelines, and interest on withheld amounts.

Are pay-when-paid and pay-if-paid clauses enforceable?

Pay-when-paid clauses β€” which set a reasonable outer payment deadline but condition timing on the prime receiving client payment β€” are generally enforceable in most US states and Canadian provinces. Pay-if-paid clauses β€” which make the subcontractor bear the full risk of client non-payment indefinitely β€” are void or unenforceable in California, New York, Wisconsin, Maryland, and several other jurisdictions. Always check the law of the project location before including either clause.

Do I need a lawyer to draft a subcontract agreement?

For straightforward commercial subcontracts under $250K in a single jurisdiction, a high-quality template reviewed against the prime contract is often sufficient. Engage a construction or commercial attorney when the subcontract value exceeds $500K, when the project involves federal government work with mandatory FAR clauses, when the subcontractor is in a different jurisdiction with unfamiliar lien and prompt-payment laws, or when the scope involves significant IP or proprietary data. A targeted review typically costs $500–$1,500 and is worthwhile on any project where a dispute would cost more.

How this compares to alternatives

vs Independent Contractor Agreement

An independent contractor agreement engages a specialist directly for services with no upstream client contract involved. A subcontract agreement sits within a contract chain β€” the prime has already committed to a client and is delegating work downstream. Subcontracts carry flow-down obligations, lien rights, retainage, and bonding provisions that a standard contractor agreement does not include. Use an independent contractor agreement when you are the end client; use a subcontract when you are the prime.

vs Consulting Agreement

A consulting agreement is typically a direct bilateral arrangement for advisory or professional services β€” there is no parent project contract, and the consultant is usually paid on time-and-materials or monthly retainer with no retainage. A subcontract agreement is appropriate when the work forms part of a larger contracted delivery and you need flow-down compliance, lien protection, bonding, and construction-standard payment terms including retention.

vs Service Agreement

A service agreement covers the ongoing provision of services between two parties β€” maintenance, support, managed services β€” without a defined project end date or upstream prime contract. A subcontract agreement is project-specific, has a defined scope and completion date, and is subordinate to a prime contract. For ongoing vendor relationships with no project delivery obligation, a service agreement is the appropriate document.

vs General Contractor Agreement

A general contractor agreement β€” also called a prime contract β€” runs between the client and the contractor who bears overall project responsibility. A subcontract agreement runs between that prime contractor and a lower-tier party performing a portion of the work. The prime contract defines the client relationship; the subcontract defines the downstream labor and delivery chain. The two documents are complementary and should be read together.

Industry-specific considerations

Construction and engineering

Trade-specific scope carve-outs, lien waivers, bonding requirements, certified payroll, and retainage are standard features on every construction subcontract.

Information technology and software

IP assignment covering custom code and data, confidentiality covering client systems access, and milestone-based payment tied to sprint deliverables or acceptance testing.

Professional services and consulting

Time-and-materials or fixed-fee structures, non-solicitation of the prime's clients, and PI insurance requirements are the primary contractual concerns.

Government and defense contracting

Mandatory FAR and DFARS flow-down clauses, small-business subcontracting plan requirements, cost-accounting standards, and security clearance conditions.

Jurisdictional notes

United States

Subcontractor lien rights are governed by state mechanic's lien statutes β€” notice deadlines, filing windows, and foreclosure procedures vary significantly by state. Most states have prompt payment acts setting maximum payment periods and interest penalties; several also cap or regulate retainage rates. Anti-indemnity statutes in California, Texas, Florida, and other states prohibit broad-form indemnity shifting the prime's own negligence to the subcontractor. Pay-if-paid clauses are void in California, New York, and Wisconsin, among others.

Canada

Construction lien rights are governed by provincial legislation β€” Ontario's Construction Act (2018) introduced significant reforms including mandatory prompt payment (28 days from invoice) and adjudication for disputes. Most provinces prohibit pay-if-paid clauses or require minimum payment periods regardless of contractual language. Quebec's Civil Code governs construction contracts differently from common-law provinces, and French-language contracts are required for provincially regulated Quebec employers.

United Kingdom

The Housing Grants, Construction and Regeneration Act 1996 (as amended) gives all construction subcontractors a statutory right to payment in installments, a minimum payment notice period, and the right to refer disputes to adjudication within 28 days β€” any contractual terms that conflict with these rights are replaced by the Scheme for Construction Contracts. Pay-when-paid clauses are generally unenforceable except in cases of upstream insolvency. The Construction Industry Scheme (CIS) imposes tax-deduction obligations on contractors paying certain subcontractors.

European Union

The EU Late Payment Directive (2011/7/EU) sets maximum payment periods of 30 days for public contracts and 60 days for commercial contracts, with statutory interest accruing automatically on late payments. Member states implement their own construction and subcontracting laws β€” France, Germany, and Spain have mandatory written subcontract requirements for construction above certain thresholds. GDPR data protection obligations must be flowed down to subcontractors who access personal data, typically through a data processing agreement exhibit.

Template vs lawyer β€” what fits your deal?

PathBest forCostTime
Use the templatePrime contractors engaging familiar trades or vendors on straightforward projects under $250K in a single jurisdictionFree30–60 minutes
Template + legal reviewProjects over $250K, multi-jurisdiction subcontracts, or government prime contracts requiring FAR flow-down clauses$500–$1,5002–5 days
Custom draftedLarge construction or infrastructure projects over $5M, federal defense subcontracts, or subcontracts involving significant IP or cross-border regulatory exposure$2,000–$8,000+1–3 weeks

Glossary

Prime Contractor
The party that holds the main contract with the client and is legally responsible for the entire project, including work delegated to subcontractors.
Subcontractor
A company or individual engaged by the prime contractor to perform a defined portion of the project work under the authority of the prime contract.
Flow-Down Clause
A provision that passes specific obligations from the prime contract β€” such as safety standards, compliance requirements, or IP terms β€” down to the subcontractor.
Retention
A percentage of each progress payment (typically 5–10%) held back by the prime contractor until the subcontractor's work is substantially complete and accepted.
Scope of Work
A detailed written description of the specific tasks, deliverables, standards, and exclusions that define exactly what the subcontractor is responsible for.
Change Order
A written amendment to the subcontract authorizing a modification to the scope, schedule, or price β€” required before any out-of-scope work is performed.
Indemnification
A contractual obligation requiring one party to compensate the other for losses, liabilities, or legal costs arising from specified events β€” typically the indemnifying party's negligence.
Lien Waiver
A document signed by the subcontractor releasing its right to file a mechanic's lien against the project property upon receiving a progress or final payment.
Liquidated Damages
A pre-agreed sum the subcontractor pays for each day of delay beyond the contracted completion date, replacing the need to prove actual damages.
Substantial Completion
The point at which the subcontractor's work is sufficiently complete that it can be used for its intended purpose, even if minor punch-list items remain.
Pay-When-Paid Clause
A provision that conditions the subcontractor's right to payment on the prime contractor first receiving payment from the client β€” enforceability varies by jurisdiction.
Surety Bond
A three-party guarantee in which a bonding company promises to complete or financially cover a subcontractor's obligations if the subcontractor defaults.

Part of your Business Operating System

This document is one of 3,000+ business & legal templates included in Business in a Box.

  • Fill-in-the-blanks β€” ready in minutes
  • 100% customizable Word document
  • Compatible with all office suites
  • Export to PDF and share electronically

Create your document in 3 simple steps.

From template to signed document β€” all inside one Business Operating System.
1
Download or open template

Access over 3,000+ business and legal templates for any business task, project or initiative.

2
Edit and fill in the blanks with AI

Customize your ready-made business document template and save it in the cloud.

3
Save, Share, Send, Sign

Share your files and folders with your team. Create a space of seamless collaboration.

Save time, save money, and create top-quality documents.

β˜…β˜…β˜…β˜…β˜…

"Fantastic value! I'm not sure how I'd do without it. It's worth its weight in gold and paid back for itself many times."

Managing Director Β· Mall Farm
Robert Whalley
Managing Director, Mall Farm Proprietary Limited
β˜…β˜…β˜…β˜…β˜…

"I have been using Business in a Box for years. It has been the most useful source of templates I have encountered. I recommend it to anyone."

Business Owner Β· 4+ years
Dr Michael John Freestone
Business Owner
β˜…β˜…β˜…β˜…β˜…

"It has been a life saver so many times I have lost count. Business in a Box has saved me so much time and as you know, time is money."

Owner Β· Upstate Web
David G. Moore Jr.
Owner, Upstate Web

Run your business with a system β€” not scattered tools

Stop downloading documents. Start operating with clarity. Business in a Box gives you the Business Operating System used by over 250,000 companies worldwide to structure, run, and grow their business.

Free Forever PlanΒ Β·Β No credit card required