- Construction Manager (CM)
- The firm or individual hired to plan, coordinate, and oversee all phases of a construction project on behalf of the owner.
- Owner's Representative
- A role in which the CM acts as the agent of the property owner, making day-to-day project decisions within agreed authority limits.
- Guaranteed Maximum Price (GMP)
- A contract ceiling above which the construction manager absorbs cost overruns, giving the owner cost certainty on a project.
- Cost of the Work
- All direct project costs — labor, materials, subcontractor invoices, permits — that are reimbursable to the CM beyond the management fee.
- Preconstruction Services
- CM services provided before construction begins, including scheduling, budgeting, constructability review, and procurement planning.
- Change Order
- A written amendment to the contract that adjusts the scope, cost, or schedule after the original agreement is executed.
- Substantial Completion
- The stage at which construction is sufficiently complete for the owner to occupy or use the facility for its intended purpose.
- Retainage
- A percentage of each progress payment — typically 5–10% — withheld until substantial completion to incentivize the CM to finish punch-list items.
- Indemnification
- A contractual obligation by one party to compensate the other for specified losses, damages, or legal costs arising from the project.
- Force Majeure
- A clause excusing a party from performance obligations when extraordinary events beyond their control — floods, strikes, pandemics — prevent timely delivery.
- Liquidated Damages
- A pre-agreed dollar amount the CM pays the owner for each day the project exceeds the contractual completion date, representing estimated delay costs.
- Lien Waiver
- A document signed by a contractor or subcontractor waiving the right to file a mechanic's lien against the property in exchange for payment.